Has an electricity pole stood on your land for decades? Do overhead power lines make it difficult to build a house, restrict development or reduce the value of your property? Does an electricity company use your land even though you have never received any payment for it?
Many property owners accept this situation for years, assuming that because the electricity infrastructure was installed generations ago, nothing can now be changed.
That is not always the case.
Polish law provides ways to regulate how a utility company uses private property and, in certain circumstances, to pursue financial claims.
The Constitutional Tribunal’s judgment of 2 December 2025 in case P 10/16 has also drawn renewed attention to the position of owners whose land has been occupied by utility infrastructure for many years.
In 2026, this issue remains the subject of significant legal disputes.
However, the mere presence of an electricity pole on your land does not guarantee payment. The key question is the legal basis on which the company uses the property.
An electricity pole has stood on the land for over 30 years. Can the owner still make a claim?
Consider the following situation.
The following story is a fictional example intended to explain the legal issue.
Marek inherited a plot of approximately 3,000 square metres from his parents in a town in the Małopolska region of Poland.
A medium-voltage electricity pole has stood on the property since the late 1980s, and power lines run above a substantial part of the land.
Marek’s parents farmed the land for many years. He would now like to use part of it to build a house.
While preparing the project, however, he discovers that the existing electricity infrastructure may restrict development.
Marek checks the land and mortgage register. He finds no entry recording a transmission easement.
Nor does he have any agreement between his parents and the electricity company.
He therefore asks the company to explain the basis on which it uses his property and whether he is entitled to payment.
The company replies that it has used the land for many years and may have acquired the relevant easement by prescription.
Does this mean that the case is already lost? Must the owner really tolerate electricity infrastructure on his land without receiving any payment?
Answering these questions requires a detailed examination of the property’s history, the company’s documentation and the applicable law.
What is a transmission easement?
A transmission easement is a limited right in rem that allows an undertaking to use another person’s property within a defined scope connected with the operation of utility infrastructure.
It was introduced into the Polish Civil Code on 3 August 2008.
The main provisions are set out in Articles 305¹–305⁴ of the Civil Code.
A transmission easement may cover not only electricity poles and power lines, but also other types of utility infrastructure, such as:
- gas pipelines;
- water supply pipelines;
- sewerage systems;
- district heating infrastructure;
- telecommunications infrastructure.
Establishing an easement defines the extent to which the company may use the property, including for operating, maintaining and repairing its infrastructure or dealing with faults.
It does not mean that the company becomes the owner of the entire plot.
The owner retains ownership of the property but must take account of the restrictions arising from the easement.
A transmission easement may be established in return for appropriate remuneration. The amount payable and the extent of the burden on the property must be determined individually.
Does an electricity pole on private land always give the owner a right to compensation?
No.
Property owners often refer generally to “compensation for an electricity pole”. Legally, however, this phrase may cover several different types of claim.
Their nature, legal basis and enforcement procedure are not the same.
Before requesting payment, the first step is to establish whether the company has a valid legal basis for using the property.
This may include an easement established previously, a relevant agreement, acquisition of an easement by prescription, or an administrative decision authorising use of the land.
Depending on the property’s legal status, the owner may consider pursuing different forms of payment.
Three types of financial claim that must be distinguished
1. Remuneration for use of the property without a legal basis
The first issue concerns a period during which the company used private property without an appropriate legal basis.
In certain circumstances, the owner may seek remuneration for that use.
The legal basis may include Article 224 § 2, Article 225 and Article 230 of the Civil Code, applied with regard to Article 352 § 2.
The Supreme Court confirmed the possibility of seeking this type of remuneration from a party exercising possession of an easement in its resolution of 24 July 2013, III CZP 36/13.
However, relevant factors include whether the possessor acted in good or bad faith, the period of use, the existence of any legal basis and the limitation of claims.
It is therefore not enough simply to show that the pole has stood on the property for many years.
It is also necessary to establish whether, and for which period, the company’s use of the land gives rise to an obligation to pay.
2. Remuneration for establishing a transmission easement
The second issue concerns putting the future use of the land on a legal footing.
Under Article 305² § 2 of the Civil Code, the property owner may demand appropriate remuneration in return for establishing a transmission easement if the undertaking refuses to enter into an agreement and the easement is necessary for the use of the utility infrastructure.
The parties may agree on the scope of the easement and the amount payable. If they cannot reach an agreement, the matter may be referred to a court.
Establishing an easement defines the rules for the company’s continued use of the property and the resulting restrictions.
Remuneration may take the form of a lump sum or, in appropriate circumstances, periodic payments.
3. A reduction in the property’s value
Electricity infrastructure may affect the market value of a plot.
The route of a power line may restrict development, make subdivision more difficult, affect how the land can be used and reduce interest among prospective buyers.
This does not mean, however, that the owner is always entitled to separate compensation equal to the entire reduction in the land’s value.
A reduction in value may be one of the factors considered when determining appropriate remuneration for establishing a transmission easement.
In other situations, separate provisions may provide a basis for compensation, including rules governing restrictions on the use of property imposed by an administrative decision.
Different payments cannot automatically be added together if doing so would compensate the same financial loss twice.
Correctly identifying the legal basis of each claim is therefore fundamental to the case.
How much can you receive for an electricity pole on your land?
This is one of the most frequently asked questions.
However, there is no uniform statutory rate payable for every electricity pole.
You cannot assume in advance that an owner is entitled to PLN 500 a year, a lump sum of PLN 10,000 or a specific percentage of the value of the entire property.
The amount depends on the circumstances.
The main factors may include:
- The property’s market value — agricultural land may be valued differently from an attractive building plot.
- The type of utility infrastructure — a low-, medium- or high-voltage pole, an overhead line or an underground installation.
- The area affected by restrictions — this may include not only the pole’s footprint, but also an appropriate strip of land associated with the use of the infrastructure.
- The location of the infrastructure within the plot — equipment near a boundary may affect the property differently from a line running through its centre.
- The possibilities for construction and development — including the effect on planned projects.
- The scope of the company’s rights — including access to the infrastructure and activities necessary for its operation.
- The degree to which the owner’s use of the property is restricted — including whether the owner can continue using the land for their own purposes.
Determining the amount payable may require specialist knowledge of property valuation, land surveying and utility infrastructure.
In court proceedings, an appropriately qualified expert’s opinion often plays an important role.
The pole occupies a few square metres but restricts the use of a much larger area
Imagine two plots of identical size.
On the first, the electricity pole stands in a corner next to the road boundary, and the power lines do not prevent the planned development.
On the second, the pole stands in the centre of the property, while the power line crosses the area where the owner intended to build a house.
In both cases, the physical footprint of the pole may be similar.
However, the actual effect of the infrastructure on the use of the property may be entirely different.
Calculating remuneration solely by reference to the area occupied by the pole’s base may therefore fail to reflect the actual restrictions associated with the infrastructure.
At the same time, this does not mean that every area beneath the power lines or subject to technical restrictions should automatically be valued as though the owner had been completely deprived of its use.
The scope of the easement, building restrictions and the effect on the property’s value must each be determined separately.
The electricity company claims that it has acquired an easement by prescription
Acquisition by prescription is one of the main issues in disputes concerning utility infrastructure.
Electricity companies may argue that they have used the property for many years in a manner corresponding to the scope of an easement.
Article 292 of the Civil Code allows a land easement to be acquired by prescription where it involves the use of a permanent and visible installation. Under Article 305⁴, these rules apply accordingly to transmission easements.
As a general rule, the current prescription periods are 20 years where possession began in good faith and 30 years where it began in bad faith.
For older infrastructure, previous legislation and transitional provisions may also be relevant.
However, the age of the pole alone does not automatically establish that an easement has been acquired by prescription.
The following matters must be examined, among others:
- when use of the property corresponding to an easement began;
- the basis on which the infrastructure was installed;
- who used the infrastructure during each period;
- whether possession was transferred between successive undertakings;
- whether possession began in good or bad faith;
- whether the running of the prescription period was interrupted;
- the significance of current differences in case law.
This assessment can be particularly complicated where the infrastructure was installed before 3 August 2008.
A company’s letter invoking prescription is not equivalent to a final court ruling confirming the acquisition of an easement.
Nevertheless, acquisition by prescription occurs by operation of law once the statutory requirements are met, and the court’s ruling confirms that acquisition.
The Constitutional Tribunal’s judgment of 2 December 2025 — what does it mean for landowners?
For many years, Supreme Court case law accepted that a land easement corresponding in substance to the later statutory transmission easement could be acquired by prescription before 3 August 2008.
It also allowed earlier periods of use to be taken into account when calculating the prescription period for a transmission easement.
This approach was reflected, among other decisions, in the Supreme Court’s resolution of 22 May 2013, III CZP 18/13.
In subsequent years, however, significant doubts arose about this interpretation.
In its decision of 24 February 2023, III CZP 108/22, the Supreme Court questioned the inclusion of the period before the statutory introduction of transmission easements in the manner accepted by the previously dominant case law.
Another important development was the Constitutional Tribunal’s judgment of 2 December 2025, case P 10/16.
The Tribunal challenged the constitutionality of an interpretation of Article 292, read together with Article 285 §§ 1 and 2 of the Civil Code, that allowed utility undertakings or the State Treasury to acquire land easements corresponding in substance to transmission easements by prescription before the provisions governing transmission easements were introduced.
This judgment is significant to the debate about protecting the ownership rights of people whose land has been occupied by utility infrastructure for many years.
However, it does not automatically entitle all property owners to payment.
Transmission easements in November 2026 — why does the legal position still require caution?
According to the information available as at 18 November 2026, the Constitutional Tribunal’s judgment in case P 10/16 had not been published in the Journal of Laws.
Its legal effect is also disputed because of controversies concerning the composition of the Tribunal’s adjudicating panel.
These problems have been highlighted, among others, by the Commissioner for Human Rights, who in 2026 drew attention to the need to ensure effective protection of property owners’ rights.
Differences remain in court case law concerning the acquisition by prescription of easements corresponding to transmission easements and the effects of the Constitutional Tribunal’s judgment.
In September 2026, the Regional Court in Szczecin referred a further legal question on this issue to the Supreme Court.
Property owners should therefore treat cautiously any claims that all previous acquisitions by prescription have automatically been invalidated.
That conclusion cannot be drawn without examining the individual case.
Judgment P 10/16 may provide an important argument in defence of an owner’s rights, but it does not guarantee a favourable outcome or any particular payment.
Cases in which a final ruling on the acquisition of an easement by prescription has already been issued require particular analysis.
It should not be assumed that simply citing the Tribunal’s new judgment is sufficient to reopen concluded proceedings successfully.
Can you claim payment for earlier years after an easement has been acquired by prescription?
This is a separate and important legal issue.
In its resolution of 30 November 2016, III CZP 77/16, the Supreme Court adopted a position excluding an owner’s right to claim remuneration for use of the property during the period preceding the acquisition of a transmission easement by prescription.
In 2024, a seven-judge panel of the Supreme Court adopted resolution III CZP 103/22, stating that the loss of ownership through acquisitive prescription does not extinguish the former owner’s claim for remuneration for use of the property during the period preceding that acquisition.
However, the later resolution concerns the acquisition of ownership by prescription, rather than directly addressing transmission easements.
Its significance for disputes concerning utility infrastructure requires a separate legal assessment.
It cannot therefore automatically be assumed either that every acquisition by prescription excludes all earlier claims, or that the owner can always seek payment for the preceding period.
How far back can a claim for payment extend?
Financial claims connected with the use of property may become time-barred.
Under Article 118 of the Civil Code, the current general limitation period is six years. For claims for periodic payments and claims connected with business activity, it is three years.
Depending on the type of claim, special provisions, transitional rules and rules governing the start and end of the limitation period may also apply.
For certain claims connected with possession of property, Article 229 of the Civil Code may also be relevant. It provides for a special period calculated from the return of the property.
You cannot therefore assume that every owner of land with an electricity pole will automatically receive payment for the previous six, ten or thirty years.
It is necessary to establish the periods for which a claim actually arose, who holds that claim and whether there are obstacles to pursuing it.
It is also worth remembering that an ordinary demand for payment sent to the company does not generally interrupt the limitation period.
Nor should it be treated as an act interrupting the period for acquiring an easement by prescription.
In its resolution of 21 January 2011, III CZP 124/10, the Supreme Court addressed the significance of an owner’s application to establish a transmission easement in return for remuneration in interrupting the prescription period for that easement.
Choosing the appropriate legal step and taking it at the right time can be crucial to protecting the property owner’s interests.
There is no transmission easement in the land and mortgage register. Is that enough?
The absence of an entry in Section III of the land and mortgage register is important, but it does not by itself establish that the company has no right to use the property.
Certain rights may exist even though they are not recorded in the register.
This applies, among other situations, to certain cases of acquisition by prescription and use of property under administrative decisions.
For older infrastructure, documents issued under former expropriation legislation may be relevant, including Article 35 of the Act of 12 March 1958 on the Principles and Procedure for the Expropriation of Real Property.
For more recent projects, decisions issued under Article 124 of the Real Estate Management Act may be significant.
Checking the land and mortgage register is therefore an important first step, but it should not replace an examination of the remaining documentation.
Can you seek payment from TAURON or another electricity company?
In southern Poland, property owners often direct their claims to companies involved in electricity distribution.
Before making a claim, however, it is necessary to identify correctly who owns the particular infrastructure and who actually uses the property.
The company selling electricity is not always the same entity as the one responsible for operating the electricity infrastructure.
For older installations, it may also be necessary to trace changes in ownership and legal succession following former state-owned enterprises.
The owner should ask the appropriate entity to provide information about the legal basis for using the land, together with documentation concerning the installation and operation of the infrastructure.
Only then can the merits and scope of any potential claims be assessed.
I bought or inherited land with an electricity pole already on it. Can I still seek payment?
Yes, in certain circumstances.
Acquiring property on which electricity infrastructure was already present does not, in itself, rule out seeking the establishment of a transmission easement in return for remuneration.
However, claims relating to the period before acquisition must be distinguished from the current owner’s rights.
When a plot is purchased, the previous owner’s earlier financial claims do not automatically transfer to the buyer simply because the buyer has acquired the property.
The position may differ in the case of inheritance, where certain financial rights of the deceased may pass to the heirs.
It may also matter whether the previous owner has already received remuneration for establishing an easement and whether the company’s right validly burdens the property.
Each of these situations requires a separate assessment.
Can you demand that an electricity pole be removed or relocated?
Obtaining payment is not always the owner’s main priority.
Sometimes the most important objective is to build a house, subdivide the plot or develop the property in another way.
Depending on the circumstances, the owner may consider claims arising from interference with ownership, including under Article 222 § 2 of the Civil Code.
However, if the company has a valid legal basis for using the property, the ability to demand removal of the infrastructure may be significantly restricted.
In certain situations, provisions governing changes to the scope of an existing easement or the manner in which it is exercised may also be relevant.
Technical feasibility, safety requirements, the cost of altering the network, the company’s interests and the legal basis for the infrastructure’s continued presence must all be considered.
There is no general rule requiring an electricity company to relocate a pole at its own expense in every situation.
Before starting a construction project, it is worth establishing both the legal and technical possibilities for changing the route of the electricity infrastructure.
Do not attempt to move, remove or interfere with electricity infrastructure yourself.
What documents should you prepare before meeting a lawyer?
A reliable assessment of a transmission easement case requires gathering the property documentation as fully as possible.
It is useful to prepare:
- The property’s land and mortgage register number.
- The cadastral plot number and cadastral district designation.
- A document confirming acquisition of the property — for example, a notarial deed or a court order confirming acquisition of an inheritance.
- A map showing the route of the utility infrastructure, if available.
- Current photographs of the poles, power lines or other installations, taken from a safe distance.
- Information about approximately when the infrastructure was installed.
- Previous correspondence with the electricity company.
- Available agreements, administrative decisions and court rulings concerning use of the property.
- Information about the land’s designated use and any planned development.
- Documentation of any obstacles to construction or development.
The owner will not always have all of these documents.
Particularly where infrastructure was installed several decades ago, a substantial part of the documentation may be held in archives or by the company.
The absence of documents does not necessarily mean that a legal assessment is impossible.
The company is offering a lump sum. Should you sign the agreement?
A settlement or agreement with a utility company may help avoid lengthy court proceedings.
Before signing, however, it is important to examine not only the amount offered but also the scope of the right being established.
Particular attention should be paid to the area covered by the easement, access arrangements, the works the company may carry out and provisions for remedying damage caused during the operation of the infrastructure.
It is also important to establish whether the proposed payment relates solely to establishing a transmission easement or whether the agreement also settles earlier use of the property.
Some settlements may include clauses waiving further claims.
Signing without prior analysis may result in losing the ability to pursue certain payments in the future.
Before accepting the company’s proposal, check both its financial and legal implications.
Frequently asked questions about electricity poles and transmission easements
Is payment due for every electricity pole on private land?
No. Entitlement to payment depends primarily on the legal basis for using the property, the type of claim and the circumstances of the individual case.
Can I receive payment if the pole has been there since the communist era?
In certain cases, yes. However, the documentation, any acquisition by prescription, administrative decisions and current case law must be examined.
Did the Constitutional Tribunal’s judgment of 2 December 2025 invalidate all acquisitions of easements by prescription?
No such general conclusion can be drawn. The significance of judgment P 10/16 for a particular case requires analysis, including because of doubts about its legal effects and differences in case law.
Can I receive payment every year?
In appropriate circumstances, remuneration for establishing a transmission easement may take the form of periodic payments. This does not mean that every owner is automatically entitled to an annual payment for a pole.
Does the absence of an easement in the land and mortgage register mean that the company is using the land unlawfully?
Not always. The legal basis for use may also arise from other circumstances, including administrative decisions or acquisition by prescription.
Can I seek payment if only power lines cross my land and the pole stands on a neighbouring property?
A claim may also be justified where utility infrastructure affects a property without a pole physically standing on it. However, the extent of use, the related restrictions and the legal basis must be established.
Can a transmission easement also be established for a gas or water pipeline?
Yes. The provisions on transmission easements are not limited to electricity infrastructure. They may also apply to other utility infrastructure referred to in the Civil Code.
Should I accept the company’s first offer?
Before accepting an offer, check the amount, the scope of the proposed easement and any provisions settling earlier claims.
Your land, your ownership rights
Electricity infrastructure is essential to households, businesses and the wider economy.
However, a utility company’s interests should not be considered separately from the rights of the private property owner.
For many years, an owner may bear the consequences of a pole, gas pipeline or other infrastructure restricting the use of their property.
At the same time, entitlement to remuneration or compensation cannot be assessed solely on the assumption that a company should pay simply because its infrastructure is present.
The applicable law, the property’s history, the company’s documentation and the actual restrictions on use must all be examined.
Often, the first and most important step is not to calculate how much to demand, but to establish which rights the property owner actually has.
Legal assistance with transmission easement matters
Cases concerning utility infrastructure often require knowledge of civil law, property law, court procedure and administrative regulations.
Angelika Mazur-Kubowicz’s Law Firm provides legal assistance with the protection of ownership rights, easements and financial claims connected with the use of property.
Assistance may include establishing the legal basis for the company’s use of the property, analysing an argument based on prescription, assessing the merits of financial claims, preparing correspondence and court documents, and providing representation in court.
The firm operates in Kraków, Proszowice and Mszana Dolna.
If electricity poles, power lines, gas pipelines or other utility infrastructure are located on your property, find out about the firm’s legal assistance in civil and inheritance matters.
Legal position as at 18 November 2026.
This article is for information purposes. Assessing the possibility of seeking remuneration, compensation or the establishment of a transmission easement requires an individual analysis of the property’s legal status, the utility infrastructure documentation and current case law.